ORIGINAL AUTHORED SLIDE CONTENT, NOT CLAUDE OUTPUT

Slide 1: North Street Studio weekly review
September 28 through October 2, 2026. Status snapshot: noon October 2. Purpose: review completed work and decide follow-up ownership. Fictional teaching example.

Slide 2: Completed job value is USD 1,080
Completed: 4 jobs, USD 1,080. Scheduled: 1 job, USD 420. Cancelled: 1 job, USD 120. The completed-value measure excludes scheduled and cancelled amounts.

Slide 3: Cedar contributes USD 420 of completed value
Cedar: USD 420. Pine: USD 360. Birch: USD 300. Combined completed value: USD 1,080.

Slide 4: Two follow-ups need an owner
Cedar requests a follow-up on October 6; owner unassigned. Pine's NS105 completion timing remains unconfirmed; follow-up owner unassigned. Birch cancellation reason is not supplied.

Slide 5: Decide who will take the next actions
Proposed decision: assign an owner for Cedar's October 6 follow-up. Proposed decision: assign an owner to confirm NS105 timing with Pine. Record any new assignment after the meeting.