ORIGINAL AUTHORED COMPARISON, NOT A CLAUDE RESPONSE
Week one September 28 through October 2, noon October 2: completed 4 / USD 1,080; scheduled 1 / USD 420; cancelled 1 / USD 120.
Week two October 5 through October 9, noon October 9: completed 4 / USD 1,160; scheduled 2 / USD 600; cancelled 1 / USD 130.
Completed change USD 80. Percentage relative to week one: 80 / 1080 * 100, rounded to one decimal = 7.4 percent. Completed count unchanged at four.
Scheduled change USD 180. Cancelled change USD 10. These are separate measures.
No cause, durable trend, forecast, cash receipts, or profit is established.